Wednesday, September 14, 2016




ABCDEFGHIJKLMN
1
VacationHouseProductionSchedule
2
MondaysSept 19Sept 26Oct 3Oct 10Oct 17Oct 24Oct 31Nov 7Nov 14Nov 21Nov 28Dec 5Dec 12
3
Week12345678910111213
4
Modeling
5
Surfacing
6
Rigging
7
Layout
8
Animation
9
Rendering
10
Compositing




Production Budget
Vacation House

  • Modeling
    • House - 2 weeks
    • Environment - 2 weeks
    • Other - 1 weeks
  • Surfacing
    • House - 2.5 weeks
      • UV unwrapping - 4 days
      • Texture painting - 8 days
      • Shaders 5 days
    • Environment - 2.5 weeks
      • UV unwrapping - 4 days
      • Texture painting - 8 days
      • Shaders 5 days
  • Layout - 4 weeks
    • Blocking/timing 1 week
    • Layout final 3 weeks
  • Animation
    • House 2 weeks
      • Running
    • Other
      • Car
        • 1  week
    • VFX
      • Water 1- week
  • Rendering
    • Test renders - 1 week
    • Renders - 3 weeks
  • Compositing 1 - 2 weeks
    • Re-renders at same time